甲骨文裁员2.1万人后，其为OpenAI建设的威斯康星州近1吉瓦数据中心项目遭遇监管障碍。州监管机构要求甲骨文为该项目超70亿美元的电力基础设施提供担保，但甲骨文信用评级已降至BBB-，低于要求水平。若采用信用证担保，每年成本将超1亿美元。

## 正文

Oracle cut its workforce by 21，000， and now faces a $7 billion hurdle for an OpenAI data center.

Oracle is building a nearly one-gigawatt campus in Wisconsin as part of its $300 billion cloud deal with OpenAI.

But state regulators want Oracle to guarantee more than $7 billion of the power infrastructure built for the project. Oracle's credit rating has fallen to BBB-， below the required level. A letter of credit could cost the company over $100 million every year.

While Oracle continues to lose value， SpaceX is gaining importance as a hyperscaler.