Nvidia 向软银旗下数据中心开发商 SB Energy 投资 15 亿美元

TechCrunch:AI(RSS)·2026-08-17 23:16·19天前·Tim De Chant
AI 导读

Nvidia 周一宣布向软银与 OpenAI 关联的数据中心开发商 SB Energy 投资 15 亿美元,并成为 OpenAI 位于俄亥俄州辛辛那提附近 Ports-Pike 数据中心计算基础设施的唯一供应商。

TechCrunch:AI(RSS)
63AI 编辑部评分,满分 100

Nvidia 向软银旗下数据中心开发商 SB Energy 投资 15 亿美元

2026-08-17 23:16· 19天前· Tim De Chant
AI 导读

Nvidia 周一宣布向软银与 OpenAI 关联的数据中心开发商 SB Energy 投资 15 亿美元,并成为 OpenAI 位于俄亥俄州辛辛那提附近 Ports-Pike 数据中心计算基础设施的唯一供应商。

Nvidia said on Monday that it will invest $1.5 billion in SB Energy, a data center linked to SoftBank and OpenAI.

The investment ensures that Nvidia will be the sole supplier of compute infrastructure at OpenAI’s Ports-Pike data center near Cincinnati, Ohio. Nvidia will also provide up to $105 billion in credit to help build the facility, which could scale from an initial 4.25 gigawatts to 8 gigawatts in size, according to documents the company filed with the SEC.

SB Energy’s existing investors include SoftBank and OpenAI. SoftBank had previously held $5.8 billion worth of Nvidia stock, which it sold in November to help fund other AI investments.

The data center and power developer will build a 9.2 gigawatt natural gas power plant on the site, which is land owned by the U.S. Department of Energy. The site previously enriched uranium for the U.S. nuclear arsenal and for U.S. Navy submarines.

The power plant is expected to cost $33 billion. The steep sum reflects the skyrocketing costs of building natural gas power plants, which have risen 66% in the last two years, according to BloombergNEF.

By the time SB Energy’s power plant and others are completed, they’ll be competing for natural gas with export markets, a confluence that could triple natural gas prices in some parts of the country.

来源:TechCrunch:AI(RSS)· techcrunch.com